Issue 2026-003 | Issue date: 2026-10-19 | Reporting period: 2026-10-12–2026-10-18 | Price snapshots checked: 2026-10-19. Comparisons use the October 12 briefing. This issue establishes the first site-level data-center baseline; older announcements are not new weekly supply.

Three actionable developments

  1. B300 rack design needs a fresh deployment check. Supermicro's October 13 OCP launch adds 2OU, eight-GPU B300 nodes on ORv3/48V DC, up to 18 nodes/144 GPUs per rack. Recheck utilities before comparing conventional rack quotes. This verifies specifications, not Asian stock or delivery slots. Official source
  2. Data-center financing and ownership are changing, without verified new vacancy. DayOne announced approximately USD7.2bn of Malaysia financing on October 14; PDG signed an agreement to sell five Indonesian enterprise sites on October 12, subject to closing. Validate phase delivery and the eventual service counterparty. DayOne / PDG
  3. The GB300 public rental snapshot moved higher. Verda lists USD11.71/GPU/hour versus 10.95 in the previous snapshot: +6.94%. RunPod and Nebius prices below are unchanged. The effective date is undisclosed; obtain region- and term-specific conditions. Verda

GPU supply, purchase pricing and lead times

No independently verifiable physical inventory quantities, OEM available-to-promise allocations, delivered purchase prices or binding lead times were obtained for B300, GB300, H200 or H100 in Singapore, Malaysia, Indonesia or Thailand. Availability announcements, reseller listings and cloud prices do not establish purchasable stock. No hardware price/lead-time change is asserted; historical inventory documents are not assumed valid.

Comparable purchase offers need configuration, quantity, new/refurbished condition, PCIe/SXM, server/rack scope, destination, taxes/freight and validity, supported by physical-stock evidence or direct OEM allocation confirmation.

OEM and channels

Supermicro OCP portfolio — October 13, 2026; global relevance. The advertised 250kW CDU rating is cooling capability, not rack electrical consumption or deployable GPU quantity. Asian allocations, prices and lead times were not disclosed. Match ORv3, DC power, CDU placement, facility-water temperature/flow, floor loading and the full network BOM to the site. Evidence: strong official technical disclosure; commercial delivery unverified. Source

No material, quantified new four-market ATP or binding lead-time disclosure was verified from Dell, HPE or ASUS; this does not establish absence of supply.

Asian data centers and rentable capacity

Rolling horizons: near term through January 19, 2027; medium term January 20–October 19, 2027; longer term thereafter. Every site's vacant IT MW, reservable quantity and current rent remain unverified. The figures below describe campus/design or historical phases. Operating does not mean vacant.

Horizon / market / siteEvidence / delivery status
Near / Malaysia / AirTrunk JHB1Operating; 150+MW campus, not vacancy. Liquid cooling; design PUE 1.15. Confirm vacant hall, CDU and SLA. Operator source
Near / Indonesia / NTT DATA Jakarta 3Operating first building 15MW; full build-out 45MW. A 2023 sheet lists 5–15kW/rack. Refresh liquid-cooling/high-density suitability. Operator source
Near / Thailand / ST Telemedia GDC Bangkok 1Operating; 23MW IT design. Direct-to-chip/immersion support; base air cooling 12kW/rack. Verify installed cooling and vacant racks. Operator source
Medium / Thailand / ST Telemedia GDC Bangkok 2Under development; Q1 2027 target, 24MW design. Liquid cooling; design PUE 1.3. Quarter straddles near/mid windows; confirm monthly RFS. Operator source
Near / Singapore / DayOne SG120MW allocation; historical Q4 2026 first-phase target. Current energization/RFS unverified. Obtain refreshed delivery evidence. Operator source
Medium / Malaysia / Equinix JH2Topped out; Q3 2027 target; 2,225 planned cabinets, not vacancy. Verify phase power, density and cooling. Operator source
Near / Japan / Princeton Digital Group TY1Launched 2025-04-24; 96MW campus, not all delivered/vacant. Up to 140kW/rack, liquid cooling, PUE below 1.34. Confirm building availability. Operator source
Near / South Korea / ST Telemedia GDC Seoul 1Commercial operation June 2026; up to 30MW design, not vacancy. Verify liquid cooling, rack density and international network. Operator source
Near / Taiwan / Vantage TPE11Opened 2024-07-10; announcement: 16MW, liquid cooling. Official search text retrieved; live-page fetch failed. Refresh phase facts. Operator source
Near / Hong Kong / NTT DATA Tai PoOperating; 9.9MW critical IT; up to 12kVA/rack, not kW. Verify power factor and high-density retrofit before GPU placement. Operator source
Near / India / Princeton Digital Group MU1Current portfolio lists 150MW/five buildings; historical documents differ. Reconcile operating phases and IT-power basis. Operator source
Long / Japan / DayOne ImariAnnounced 2026-10-02; first phase targeted 2030. 200MW grid/160MW powered-land resources are not rentable IT load. Long-term BD only. Operator source

Site source dates: JHB1 undated current page (opening announcement July 30, 2024); Jakarta3 2023 sheet/April 2022 opening; Bangkok1 undated page; Bangkok2 October 22, 2025 sheet; SG1 undated page/historical October 11, 2024 announcement; JH2 November 11, 2025 article body; TY1 April 24, 2025; Seoul1 June 16, 2026; TPE11 July 10, 2024; Tai Po and MU1 undated pages; Imari October 2, 2026. All checked October 19. Site-level capacity, cooling and price qualifications remain outstanding. Bangkok2's Q1 window straddles near/medium horizons and is provisionally tracked as medium.

Weekly operator signals

Historical market baseline, not new offers. CBRE's June 17, 2026 report, covering Q1 and a 250–500kW requirement, lists monthly asking rents: Singapore USD330–475/kW, average 403; Tokyo average 280; Hong Kong 295. Electricity/PUE, taxes, installation, deposits, cross-connects, networking, liquid cooling and operations scope were not verified. These are not October site quotes. No comparable verified public Johor/Jakarta/Bangkok rent was obtained. Cushman's H1 2026 update reports APAC vacancy falling from 10.9% in H2 2025 to 10.3%; this does not establish current site vacancy. Evidence: historical industry research, moderate. CBRE / Cushman

Before placement, qualify minimum commitment, term/deposit, quote validity, powered IT load, anchor-customer occupation, CDU/water conditions, redundancy/SLA, carriers and measured cross-border latency.

Mainland China is separate. No compliant, deliverable capacity-and-GPU offer was verified for these models. An operating facility does not establish lawful deployment for a particular product/customer.

GPU leasing economics

October 19 public on-demand observations, normalized only to USD/GPU/hour; neither hardware purchase prices nor guaranteed Asian long-term capacity.

Provider / productH100H200B300GB300Weekly comparison
RunPod Secure Pods3.99 / 80GB SXM5.29 / 141GB8.99 / 288GBNot verifiedThree listed models unchanged
Nebius HGX4.505.409.50Contact salesThree listed models unchanged
Verda on-demand4.296 / 80GB SXM55.602 / 141GB SXM510.18 / 268GB SXM6, as listed11.71 / 288GB SXM6GB300: 10.95 to 11.71, +6.94%; no matched prior primary-source baseline for others

RunPod marks its page updated October 8. Nebius and Verda give no effective date/validity for these observed prices. Verda's GB300 product page describes Nordic hosting, not Asian inventory. GPU memory, CPU/RAM, instance/cluster and network scope differ; this is not a cheapest-provider ranking.

Taxes, deposits, guaranteed Asian region/quantity and commercial validity remain unverified. Confirm storage, egress, support and RoCE/IB/NVLink topology. Obtain matched-region/term total-cost offers. No payback estimate is made without purchase cost, achieved utilization, capital cost and realizable residual value.

Cross-border compliance

No new material formal rule effective October 12–18 was verified for the priority markets. Dynamic official-search coverage was incomplete; this is not a comprehensive transaction clearance. These are existing/future-effective checkpoints, not new weekly rules:

No material new Indonesian/Thai measure was verified; no party is cleared by this report. Used equipment and returns do not automatically escape controls.

ITAD opportunities

No verified weekly H100/H200 completed resale prices, bulk retirement inventory, warranty-transfer changes or new sanitization/cross-border recovery rules were obtained. Marketing buyback indications are insufficient for a residual-value curve.

Assessing recovery routes for equipment from operating-site refreshes or relocations requires verified title/serials, complete PCIe/SXM/server configuration, test logs, OEM warranty-transfer eligibility, persistent-media sanitization records and chain of custody. This is analysis, not an available lot.

Sources & Coverage

Official technical/regulatory disclosures, public price observations, historical research and analysis are labeled separately. All sources checked October 19. Undated pages are not assigned publication dates. Vantage's live-page fetch failed; official search text was available. Jakarta's technical sheet is old; MU1 phase definitions need reconciliation. No physical inspection, binding quote, verified site vacancy or complete commercial scope was obtained.